— Project Summary

Queue ID
MISO-J4167
Capacity
250 MW
Technology
Battery
Status
active
Location
Allegan, MI
Region
MISO
Developer
IA Status

BetaActiveBattery StorageMISOLive · MISO

250 MW storage in Allegan, MI · In queue since September 2025

250 MW

Capacity

0

Components

6 months

In Queue

IA Status

Interconnection Timeline

Total Duration

6 months

Pre-Study0%
Queue EntrySep 17, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

MI

County

Allegan

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

ARGENTA

Data Source

Live · MISO

No news available for this project.