BetaActiveGasMISOLive · MISO
55 MW generation in Ottawa, MI · In queue since August 2025
55 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
7 months
Pre-Study0%
Queue EntryAug 13, 2025
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MI
County
Ottawa
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
ROOSEVELT
Data Source
Live · MISO
No news available for this project.