— Project Summary

Queue ID
MISO-J4148
Capacity
245 MW
Technology
Solar
Status
active
Location
Clay, MN
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLive · MISO

245 MW generation in Clay, MN · In queue since October 2025

245 MW

Capacity

0

Components

5 months

In Queue

IA Status

Interconnection Timeline

Total Duration

5 months

Pre-Study0%
Queue EntryOct 3, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

MN

County

Clay

Region

MISO

Developer

Utility

GREAT RIVER ENERGY

Entity

MISO

Point of Interconnection

ALEXANDRIA - BISON 345.0kV

Data Source

Live · MISO

No news available for this project.