— Project Summary

Queue ID
MISO-J4051
Capacity
220 MW
Technology
Solar
Status
active
Location
Jefferson Davis, LA
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLive · MISO

220 MW generation in Jefferson Davis, LA · In queue since September 2025

220 MW

Capacity

0

Components

6 months

In Queue

IA Status

Interconnection Timeline

Total Duration

6 months

Pre-Study0%
Queue EntrySep 2, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

LA

County

Jefferson Davis

Region

MISO

Developer

Utility

Entity

MISO

Point of Interconnection

NELSON 500 SWYD - RICHARD 500.0kV

Data Source

Live · MISO

No news available for this project.