— Project Summary

Queue ID
MISO-J4046
Capacity
100 MW
Technology
Solar
Status
active
Location
Attala, MS
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLive · MISO

100 MW generation in Attala, MS · In queue since July 2025

100 MW

Capacity

0

Components

8 months

In Queue

IA Status

Interconnection Timeline

Total Duration

8 months

Pre-Study0%
Queue EntryJul 17, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

MS

County

Attala

Region

MISO

Developer

Utility

ENTERGY MISSISSIPPI, LLC.

Entity

MISO

Point of Interconnection

CONEHOMA CREEK - CARTHAGE (MS) 115.0kV

Data Source

Live · MISO

No news available for this project.