— Project Summary

Queue ID
MISO-J4006
Capacity
289.8 MW
Technology
Wind
Status
active
Location
Ringgold, IA
Region
MISO
Developer
IA Status

BetaActiveWindMISOLive · MISO

289.8 MW generation in Ringgold, IA · In queue since May 2025

289.8 MW

Capacity

0

Components

10 months

In Queue

IA Status

Interconnection Timeline

Total Duration

10 months

Pre-Study0%
Queue EntryMay 7, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

IA

County

Ringgold

Region

MISO

Developer

Utility

MIDAMERICAN ENERGY CO.

Entity

MISO

Point of Interconnection

Orient - Denny 345kV

Data Source

Live · MISO

No news available for this project.