— Project Summary

Queue ID
MISO-J4000
Capacity
343 MW
Technology
Solar
Status
active
Location
Scott, IL
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLive · MISO

343 MW generation in Scott, IL · In queue since April 2025

343 MW

Capacity

0

Components

11 months

In Queue

IA Status

Interconnection Timeline

Total Duration

11 months

Pre-Study0%
Queue EntryApr 29, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

IL

County

Scott

Region

MISO

Developer

Utility

AMEREN TRANSMISSION COMPANY OF ILLINOIS

Entity

MISO

Point of Interconnection

7MEREDOSIA - 7TURNER 345.0kV

Data Source

Live · MISO

No news available for this project.