— Project Summary

Queue ID
MISO-J3999
Capacity
1540 MW
Technology
Gas
Status
active
Location
Vermillion, IN
Region
MISO
Developer
IA Status

BetaActiveGasMISOLive · MISO

1,540 MW generation in Vermillion, IN · In queue since April 2025

1,540 MW

Capacity

0

Components

11 months

In Queue

IA Status

Interconnection Timeline

Total Duration

11 months

Pre-Study0%
Queue EntryApr 14, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

IN

County

Vermillion

Region

MISO

Developer

Utility

DUKE ENERGY INDIANA, LLC

Entity

MISO

Point of Interconnection

Sugar Creek - Cayuga CT 345.0kV

Data Source

Live · MISO

No news available for this project.