— Project Summary

Queue ID
MISO-J3978
Capacity
200 MW
Technology
Other
Status
active
Location
Sullivan, IN
Region
MISO
Developer
IA Status

BetaActiveHybridMISOLive · MISO

200 MW generation in Sullivan, IN · In queue since April 2025

200 MW

Capacity

0

Components

11 months

In Queue

IA Status

Interconnection Timeline

Total Duration

11 months

Pre-Study0%
Queue EntryApr 8, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

IN

County

Sullivan

Region

MISO

Developer

Utility

DUKE ENERGY INDIANA, LLC

Entity

MISO

Point of Interconnection

Petersburg - Sullivan (AEP/PJM) 345.0kV

Data Source

Live · MISO

No news available for this project.