BetaActiveBattery StorageMISOLive · MISO
250 MW storage in Sanilac, MI · In queue since March 2025
250 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1 year
Pre-Study0%
Queue EntryMar 31, 2025
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MI
County
Sanilac
Region
MISO
Developer
—
Utility
ITC
Entity
MISO
Point of Interconnection
GREENWOOD - RAPSON 345.0kV
Data Source
Live · MISO
No news available for this project.