— Project Summary

Queue ID
MISO-J3962
Capacity
165 MW
Technology
Other
Status
active
Location
Bay, MI
Region
MISO
Developer
IA Status

BetaActiveHybridMISOLive · MISO

165 MW generation in Bay, MI · In queue since March 2025

165 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 12, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

MI

County

Bay

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

BAUER - HAMPTON 1 345.0kV

Data Source

Live · MISO

No news available for this project.