200 MW generation in Lac qui Parle, MN · In queue since April 2025
200 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
11 months
Pre-Study0%
Queue EntryApr 8, 2025
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MN
County
Lac qui Parle
Region
MISO
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Point of Interconnection
Big Stone South - Deuel County 345.0kV
Data Source
Live · MISO