— Project Summary

Queue ID
MISO-J3942
Capacity
365 MW
Technology
Solar
Status
active
Location
Vigo, IN
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLive · MISO

365 MW generation in Vigo, IN · In queue since February 2025

365 MW

Capacity

0

Components

1y 1m

In Queue

IA Status

Interconnection Timeline

Total Duration

1y 1m

Pre-Study0%
Queue EntryFeb 20, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

IN

County

Vigo

Region

MISO

Developer

Utility

DUKE ENERGY INDIANA, LLC

Entity

MISO

Point of Interconnection

Sandford

Data Source

Live · MISO

No news available for this project.