BetaActiveSolarMISOLive · MISO
386 MW generation in Beauregard, LA · In queue since April 2025
386 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
11 months
Pre-Study0%
Queue EntryApr 1, 2025
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
LA
County
Beauregard
Region
MISO
Developer
—
Utility
CLECO POWER LLC
Entity
MISO
Point of Interconnection
COLE to PENTON 230.0 kV
Data Source
Live · MISO
No news available for this project.