— Project Summary

Queue ID
MISO-J3929
Capacity
250 MW
Technology
Wind
Status
active
Location
Audrain, MO
Region
MISO
Developer
IA Status

BetaActiveWindMISOLive · MISO

250 MW generation in Audrain, MO · In queue since January 2025

250 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection Timeline

Total Duration

1y 2m

Pre-Study0%
Queue EntryJan 31, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

MO

County

Audrain

Region

MISO

Developer

Utility

AMEREN MISSOURI

Entity

MISO

Point of Interconnection

SPENCER CREEK

Data Source

Live · MISO

No news available for this project.