BetaActiveHybridMISOLive · MISO
300 MW generation in Newton, IN · In queue since February 2025
300 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1y 1m
Pre-Study0%
Queue EntryFeb 28, 2025
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
IN
County
Newton
Region
MISO
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY LLC
Entity
MISO
Point of Interconnection
Other_
Data Source
Live · MISO
No news available for this project.