— Project Summary

Queue ID
MISO-J3910
Capacity
300 MW
Technology
Other
Status
active
Location
Newton, IN
Region
MISO
Developer
IA Status

BetaActiveHybridMISOLive · MISO

300 MW generation in Newton, IN · In queue since February 2025

300 MW

Capacity

0

Components

1y 1m

In Queue

IA Status

Interconnection Timeline

Total Duration

1y 1m

Pre-Study0%
Queue EntryFeb 28, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

IN

County

Newton

Region

MISO

Developer

Utility

NORTHERN INDIANA PUBLIC SERVICE COMPANY LLC

Entity

MISO

Point of Interconnection

Other_

Data Source

Live · MISO

No news available for this project.