BetaActiveSolarMISOLive · MISO
60 MW generation in Knox, IN · In queue since February 2025
60 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1y 1m
Pre-Study0%
Queue EntryFeb 7, 2025
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
IN
County
Knox
Region
MISO
Developer
—
Utility
DUKE ENERGY INDIANA, LLC
Entity
MISO
Point of Interconnection
Gibson Sta - Bedford 345 345.0kV
Data Source
Live · MISO
No news available for this project.