— Project Summary

Queue ID
MISO-J3880
Capacity
200 MW
Technology
Solar
Status
active
Location
Clay, IL
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLive · MISO

200 MW generation in Clay, IL · In queue since February 2025

200 MW

Capacity

0

Components

1y 1m

In Queue

IA Status

Interconnection Timeline

Total Duration

1y 1m

Pre-Study0%
Queue EntryFeb 10, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

IL

County

Clay

Region

MISO

Developer

Utility

AMEREN ILLINOIS

Entity

MISO

Point of Interconnection

7NEWTON - 7TANNER 345.0kV

Data Source

Live · MISO