87 MW generation in Vigo, IN · In queue since December 2024 · Proposed COD January 2024
87 MW
Capacity
1
Components
Gas
1y 3m
In Queue
—
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 3m
Schedule
26 months past proposed COD
Pre-Study0%
Queue EntryDec 23, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-01-26
Project Details
State
IN
County
Vigo
Region
MISO
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Point of Interconnection
SUGAR CREEK
Data Source
LBNL + Live
No news available for this project.