— Project Summary

Queue ID
MISO-J3866
Capacity
300 MW
Technology
Wind
Status
active
Location
Lapeer, MI
Region
MISO
Developer
IA Status

BetaActiveWindMISOLBNL + Live

300 MW generation in Lapeer, MI · In queue since December 2024 · Proposed COD November 2028

300 MW

Capacity

1

Components

Wind

1y 3m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 11m

Pre-Study0%
Queue EntryDec 6, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

Project Details

State

MI

County

Lapeer

Region

MISO

Developer

Utility

ITC

Entity

MISO

Point of Interconnection

BENNET - GREENWOOD 120.0kV

Data Source

LBNL + Live

No news available for this project.