BetaActiveWindMISOLBNL + Live
230 MW generation in Shiawassee, MI · In queue since December 2024 · Proposed COD November 2028
230 MW
Capacity
1
Components
Wind
1y 3m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryDec 9, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-01
Project Details
State
MI
County
Shiawassee
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
GOSS - THETFORD 345.0kV
Data Source
LBNL + Live
No news available for this project.