BetaActiveSolarMISOLBNL + Live
200 MW generation in Branch, MI · In queue since December 2024 · Proposed COD October 2028
200 MW
Capacity
1
Components
Solar
1y 3m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 10m
Pre-Study0%
Queue EntryDec 17, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-01
Project Details
State
MI
County
Branch
Region
MISO
Developer
—
Utility
GridUnity
Entity
MISO
Point of Interconnection
Other_
Data Source
LBNL + Live
No news available for this project.