— Project Summary

Queue ID
MISO-J3858
Capacity
110 MW
Technology
Solar
Status
active
Location
Livingston, MI
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLBNL + Live

110 MW generation in Livingston, MI · In queue since December 2024 · Proposed COD June 2029

110 MW

Capacity

1

Components

Solar

1y 3m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 6m

Pre-Study0%
Queue EntryDec 18, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-06-01

Project Details

State

MI

County

Livingston

Region

MISO

Developer

Utility

ITC

Entity

MISO

Point of Interconnection

Madrid Substation 120 kV - Bus number 265650

Data Source

LBNL + Live

No news available for this project.