BetaActiveSolarMISOLBNL + Live
105 MW generation in — · In queue since December 2024 · Proposed COD April 2030
105 MW
Capacity
1
Components
Solar
1y 3m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5y 4m
Pre-Study0%
Queue EntryDec 26, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-04-01
Project Details
State
—
County
—
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
ALCONA - WHITTEMORE 138.0kV
Data Source
LBNL + Live
No news available for this project.