— Project Summary

Queue ID
MISO-J3849
Capacity
200 MW
Technology
Wind
Status
active
Location
Winnebago, IA
Region
MISO
Developer
IA Status

BetaActiveWindMISOLBNL + Live

200 MW generation in Winnebago, IA · In queue since December 2024 · Proposed COD June 2030

200 MW

Capacity

1

Components

Wind

1y 3m

In Queue

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

5y 6m

Pre-Study0%
Queue EntryDec 31, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-06-30

Project Details

State

IA

County

Winnebago

Region

MISO

Developer

Utility

ITC MIDWEST

Entity

MISO

Point of Interconnection

Bison - Colby 345kV

Data Source

LBNL + Live

No news available for this project.