BetaActiveWindMISOLBNL + Live
200 MW generation in Winnebago, IA · In queue since December 2024 · Proposed COD June 2030
200 MW
Capacity
1
Components
Wind
1y 3m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5y 6m
Pre-Study0%
Queue EntryDec 31, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-06-30
Project Details
State
IA
County
Winnebago
Region
MISO
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Point of Interconnection
Bison - Colby 345kV
Data Source
LBNL + Live
No news available for this project.