BetaActiveSolarMISOLBNL + Live
150 MW generation in St. Joseph, MI · In queue since November 2024 · Proposed COD April 2029
150 MW
Capacity
1
Components
Solar
1y 4m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 5m
Pre-Study0%
Queue EntryNov 26, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-01
Project Details
State
MI
County
St. Joseph
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
BATAVIA - MORROW 138.0kV
Data Source
LBNL + Live
No news available for this project.