BetaActiveGasMISOLBNL
21 MW generation in WI · In queue since August 2014 · Proposed COD June 2015
21 MW
Capacity
1
Components
Gas
11y 7m
In Queue
IA Executed
IA Status
COD target: 2015
Interconnection Timeline
Total Duration
10 months
Schedule
132 months past proposed COD
Construction75%
Queue EntryAug 25, 2014
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2015-06-01
Project Details
State
WI
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
2346 Clearview Road, Cambridge, WI
Data Source
LBNL
No news available for this project.