BetaActiveBatteryMISOLBNL + Live
250 MW storage in Eaton, MI · In queue since October 2024 · Proposed COD October 2028
250 MW
Capacity
1
Components
Battery
1y 5m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4 years
Pre-Study0%
Queue EntryOct 24, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-06
Project Details
State
MI
County
Eaton
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
ONEIDA
Data Source
LBNL + Live
No news available for this project.