— Project Summary

Queue ID
MISO-J3836
Capacity
250 MW
Technology
Battery
Status
active
Location
Eaton, MI
Region
MISO
Developer
IA Status

BetaActiveBatteryMISOLBNL + Live

250 MW storage in Eaton, MI · In queue since October 2024 · Proposed COD October 2028

250 MW

Capacity

1

Components

Battery

1y 5m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4 years

Pre-Study0%
Queue EntryOct 24, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-06

Project Details

State

MI

County

Eaton

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

ONEIDA

Data Source

LBNL + Live

No news available for this project.