BetaActiveWindMISOLBNL + Live
200 MW generation in Cass, ND · In queue since October 2024 · Proposed COD September 2028
200 MW
Capacity
1
Components
Wind
1y 5m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryOct 1, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-01
Project Details
State
ND
County
Cass
Region
MISO
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Point of Interconnection
Buffalo 115 kV
Data Source
LBNL + Live