BetaActiveSolarMISOLBNL + Live
40 MW generation in Shelby, IL · In queue since June 2024 · Proposed COD March 2028
40 MW
Capacity
1
Components
Solar
1y 9m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 9m
Pre-Study0%
Queue EntryJun 7, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
IL
County
Shelby
Region
MISO
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Point of Interconnection
4PANA 1 - 4SHELBYVL E 138.0kV
Data Source
LBNL + Live
No news available for this project.