— Project Summary

Queue ID
MISO-J3761
Capacity
145.8 MW
Technology
Solar
Status
active
Location
Ogemaw, MI
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLBNL + Live

145.8 MW generation in Ogemaw, MI · In queue since April 2024 · Proposed COD November 2027

145.8 MW

Capacity

1

Components

Solar

1y 11m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 7m

Pre-Study0%
Queue EntryApr 5, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-11-01

Project Details

State

MI

County

Ogemaw

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

GALLAGHER - TWINING 138.0kV

Data Source

LBNL + Live

No news available for this project.