BetaActiveGasMISOLBNL + Live
4.2 MW generation in Marquette, MI · In queue since April 2024 · Proposed COD January 2019
4.2 MW
Capacity
1
Components
Gas
1y 11m
In Queue
—
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
1y 11m
Schedule
87 months past proposed COD
Pre-Study0%
Queue EntryApr 17, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2019-01-21
Project Details
State
MI
County
Marquette
Region
MISO
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Point of Interconnection
Huron
Data Source
LBNL + Live
No news available for this project.