— Project Summary

Queue ID
MISO-J3736
Capacity
100 MW
Technology
Battery
Status
active
Location
Osage, MO
Region
MISO
Developer
IA Status

BetaActiveBatteryMISOLBNL + Live

100 MW storage in Osage, MO · In queue since April 2024 · Proposed COD December 2027

100 MW

Capacity

1

Components

Battery

1y 11m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 8m

Pre-Study0%
Queue EntryApr 17, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-03

Project Details

State

MO

County

Osage

Region

MISO

Developer

Utility

AMEREN MISSOURI

Entity

MISO

Point of Interconnection

LOOSE CREEK

Data Source

LBNL + Live

No news available for this project.