BetaActiveSolarBatteryMISOLBNL + Live
150 MW hybrid in Gibson, IN · In queue since May 2024 · Proposed COD April 2028
150 MW
Capacity
1
Components
Solar
1y 10m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryMay 25, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-17
Project Details
State
IN
County
Gibson
Region
MISO
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Point of Interconnection
Oakland City - Old Ben Coal 138.0kV
Data Source
LBNL + Live
No news available for this project.