— Project Summary

Queue ID
MISO-J3688
Capacity
150 MW
Technology
Battery
Status
active
Location
White, IN
Region
MISO
Developer
IA Status

BetaActiveBatteryMISOLBNL + Live

150 MW storage in White, IN · In queue since April 2024 · Proposed COD September 2028

150 MW

Capacity

1

Components

Battery

1y 11m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 5m

Pre-Study0%
Queue EntryApr 17, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-30

Project Details

State

IN

County

White

Region

MISO

Developer

Utility

NORTHERN INDIANA PUBLIC SERVICE COMPANY

Entity

MISO

Point of Interconnection

MONTICELLO - SPRINGBORO(DUKE) 138.0kV

Data Source

LBNL + Live

No news available for this project.