— Project Summary

Queue ID
MISO-J3682
Capacity
150 MW
Technology
Solar
Status
active
Location
Muskegon, MI
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLBNL + Live

150 MW generation in Muskegon, MI · In queue since April 2024 · Proposed COD April 2028

150 MW

Capacity

1

Components

Solar

1y 11m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4 years

Pre-Study0%
Queue EntryApr 18, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-01

Project Details

State

MI

County

Muskegon

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

FOUR MILE - WHITE ROAD 138.0kV

Data Source

LBNL + Live

No news available for this project.