— Project Summary

Queue ID
MISO-J3656
Capacity
250 MW
Technology
Battery
Status
active
Location
Saginaw, MI
Region
MISO
Developer
IA Status

BetaActiveBatteryMISOLBNL + Live

250 MW storage in Saginaw, MI · In queue since March 2024 · Proposed COD June 2028

250 MW

Capacity

1

Components

Battery

2 years

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 3m

Pre-Study0%
Queue EntryMar 26, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-30

Project Details

State

MI

County

Saginaw

Region

MISO

Developer

Utility

ITC

Entity

MISO

Point of Interconnection

BAUER

Data Source

LBNL + Live

No news available for this project.