BetaActiveGasMISOLBNL + Live
650 MW generation in Sullivan, IN · In queue since April 2024 · Proposed COD September 2027
650 MW
Capacity
1
Components
Gas
1y 11m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 5m
Pre-Study0%
Queue EntryApr 18, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-01
Project Details
State
IN
County
Sullivan
Region
MISO
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Point of Interconnection
Merom (HED) - Dresser 345.0kV
Data Source
LBNL + Live
No news available for this project.