— Project Summary

Queue ID
MISO-J3586
Capacity
250.55 MW
Technology
Solar+Battery
Status
active
Location
Grenada, MS
Region
MISO
Developer
IA Status

BetaActiveSolarBatteryMISOLBNL + Live

250.55 MW hybrid in Grenada, MS · In queue since April 2024 · Proposed COD January 2028

250.55 MW

Capacity

1

Components

Solar

1y 11m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 9m

Pre-Study0%
Queue EntryApr 18, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-01-01

Project Details

State

MS

County

Grenada

Region

MISO

Developer

Utility

ENTERGY MISSISSIPPI, LLC.

Entity

MISO

Point of Interconnection

INDIANOLA 230/115 SUB - TILLATOBA 230.0kV

Data Source

LBNL + Live

No news available for this project.