— Project Summary

Queue ID
MISO-J3552
Capacity
112 MW
Technology
Solar
Status
active
Location
Mcleod, MN
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLBNL + Live

112 MW generation in Mcleod, MN · In queue since April 2024 · Proposed COD October 2028

112 MW

Capacity

1

Components

Solar

1y 11m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 6m

Pre-Study0%
Queue EntryApr 16, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-31

Project Details

State

MN

County

Mcleod

Region

MISO

Developer

Utility

MISSOURI RIVER ENERGY SERVICES - TRANSMISSION

Entity

MISO

Point of Interconnection

Hutchinson Municipal - GRE Big Swan 115.0kV

Data Source

LBNL + Live

No news available for this project.