BetaActiveBatteryMISOLBNL + Live
200 MW storage in Dubois, IN · In queue since April 2024 · Proposed COD September 2027
200 MW
Capacity
1
Components
Battery
1y 11m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 5m
Pre-Study0%
Queue EntryApr 18, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-10
Project Details
State
IN
County
Dubois
Region
MISO
Developer
—
Utility
Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
Entity
MISO
Point of Interconnection
Duff 345/138kV
Data Source
LBNL + Live
No news available for this project.