BetaActiveSolarMISOLBNL + Live
116.9 MW generation in Alcona, MI · In queue since March 2024 · Proposed COD April 2027
116.9 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 1m
Pre-Study0%
Queue EntryMar 28, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-01
Project Details
State
MI
County
Alcona
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
ALPENA - SPRUCE ROAD 138.0kV
Data Source
LBNL + Live
No news available for this project.