— Project Summary

Queue ID
MISO-J3528
Capacity
225 MW
Technology
Solar+Battery
Status
active
Location
Jasper, IL
Region
MISO
Developer
IA Status

BetaActiveSolarBatteryMISOLBNL + Live

225 MW hybrid in Jasper, IL · In queue since April 2024 · Proposed COD December 2026

225 MW

Capacity

1

Components

Solar

1y 11m

In Queue

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 8m

Pre-Study0%
Queue EntryApr 15, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-30

Project Details

State

IL

County

Jasper

Region

MISO

Developer

Utility

AMEREN ILLINOIS

Entity

MISO

Point of Interconnection

7CASEY - 7NEWTON 345.0kV

Data Source

LBNL + Live

No news available for this project.