— Project Summary

Queue ID
MISO-J351
Capacity
715 MW
Technology
Gas
Status
active
Location
IN
Region
MISO
Developer
IA Status
IA Executed

BetaActiveGasMISOLBNL

715 MW generation in IN · In queue since May 2014 · Proposed COD May 2018

715 MW

Capacity

1

Components

Gas

11y 10m

In Queue

IA Executed

IA Status

COD target: 2018

Interconnection Timeline

Total Duration

4 years

Schedule

96 months past proposed COD

Construction75%
Queue EntryMay 19, 2014

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2018-05-01

Project Details

State

IN

County

Region

MISO

Developer

Utility

Entity

MISO

Point of Interconnection

Stillwell 345 kV

Data Source

LBNL

No news available for this project.