715 MW generation in IN · In queue since May 2014 · Proposed COD May 2018
715 MW
Capacity
1
Components
Gas
11y 10m
In Queue
IA Executed
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
4 years
Schedule
96 months past proposed COD
Construction75%
Queue EntryMay 19, 2014
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2018-05-01
Project Details
State
IN
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Stillwell 345 kV
Data Source
LBNL