— Project Summary

Queue ID
MISO-J3479
Capacity
225 MW
Technology
Solar
Status
active
Location
Rapides Parish, LA
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLBNL + Live

225 MW generation in Rapides Parish, LA · In queue since April 2024 · Proposed COD February 2027

225 MW

Capacity

1

Components

Solar

1y 11m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

2y 10m

Pre-Study0%
Queue EntryApr 12, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-02-28

Project Details

State

LA

County

Rapides Parish

Region

MISO

Developer

Utility

CLECO POWER

Entity

MISO

Point of Interconnection

Hineston

Data Source

LBNL + Live

No news available for this project.