BetaActiveSolarMISOLBNL + Live
225 MW generation in Rapides Parish, LA · In queue since April 2024 · Proposed COD February 2027
225 MW
Capacity
1
Components
Solar
1y 11m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 10m
Pre-Study0%
Queue EntryApr 12, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-02-28
Project Details
State
LA
County
Rapides Parish
Region
MISO
Developer
—
Utility
CLECO POWER
Entity
MISO
Point of Interconnection
Hineston
Data Source
LBNL + Live
No news available for this project.