— Project Summary

Queue ID
MISO-J3451
Capacity
120 MW
Technology
Solar
Status
active
Location
Alcona, MI
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLBNL + Live

120 MW generation in Alcona, MI · In queue since April 2024 · Proposed COD April 2027

120 MW

Capacity

1

Components

Solar

1y 11m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3 years

Pre-Study0%
Queue EntryApr 5, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-01

Project Details

State

MI

County

Alcona

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

Other_

Data Source

LBNL + Live

No news available for this project.