— Project Summary

Queue ID
MISO-J3448
Capacity
180 MW
Technology
Wind
Status
active
Location
Grant, WI
Region
MISO
Developer
IA Status

BetaActiveWindMISOLBNL + Live

180 MW generation in Grant, WI · In queue since April 2024 · Proposed COD August 2028

180 MW

Capacity

1

Components

Wind

1y 11m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 4m

Pre-Study0%
Queue EntryApr 18, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-31

Project Details

State

WI

County

Grant

Region

MISO

Developer

Utility

DAIRYLAND POWER COOPERATIVE

Entity

MISO

Point of Interconnection

NELSON DEWEY (ATC) - GRAN GRAE (ATC) 161.0kV

Data Source

LBNL + Live