BetaActiveWindMISOLBNL + Live
180 MW generation in Grant, WI · In queue since April 2024 · Proposed COD August 2028
180 MW
Capacity
1
Components
Wind
1y 11m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 4m
Pre-Study0%
Queue EntryApr 18, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-31
Project Details
State
WI
County
Grant
Region
MISO
Developer
—
Utility
DAIRYLAND POWER COOPERATIVE
Entity
MISO
Point of Interconnection
NELSON DEWEY (ATC) - GRAN GRAE (ATC) 161.0kV
Data Source
LBNL + Live
No news available for this project.