BetaActiveWindBatteryMISOLBNL + Live
250 MW hybrid in Big Stone, MN · In queue since April 2024 · Proposed COD June 2030
250 MW
Capacity
1
Components
Wind
1y 11m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6y 2m
Pre-Study0%
Queue EntryApr 12, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-06-01
Project Details
State
MN
County
Big Stone
Region
MISO
Developer
—
Utility
MISSOURI RIVER ENERGY SERVICES - TRANSMISSION
Entity
MISO
Point of Interconnection
Other_
Data Source
LBNL + Live
No news available for this project.