— Project Summary

Queue ID
MISO-J3434
Capacity
200 MW
Technology
Solar
Status
active
Location
Kandiyohi, MN
Region
MISO
Developer
IA Status

BetaActiveSolarMISOLBNL + Live

200 MW generation in Kandiyohi, MN · In queue since March 2024 · Proposed COD September 2028

200 MW

Capacity

1

Components

Solar

2 years

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 6m

Pre-Study0%
Queue EntryMar 18, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

Project Details

State

MN

County

Kandiyohi

Region

MISO

Developer

Utility

MISSOURI RIVER ENERGY SERVICES - TRANSMISSION

Entity

MISO

Point of Interconnection

Willmar

Data Source

LBNL + Live

No news available for this project.