BetaActiveWindMISOLBNL + Live
155.6 MW generation in St. Landry Parish, LA · In queue since April 2024 · Proposed COD March 2027
155.6 MW
Capacity
1
Components
Wind
1y 11m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 11m
Pre-Study0%
Queue EntryApr 16, 2024
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-01
Project Details
State
LA
County
St. Landry Parish
Region
MISO
Developer
—
Utility
CLECO POWER
Entity
MISO
Point of Interconnection
Ville Platte - West Fork 230.0kV
Data Source
LBNL + Live
No news available for this project.