— Project Summary

Queue ID
MISO-J3394
Capacity
155.6 MW
Technology
Wind
Status
active
Location
St. Landry Parish, LA
Region
MISO
Developer
IA Status

BetaActiveWindMISOLBNL + Live

155.6 MW generation in St. Landry Parish, LA · In queue since April 2024 · Proposed COD March 2027

155.6 MW

Capacity

1

Components

Wind

1y 11m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

2y 11m

Pre-Study0%
Queue EntryApr 16, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-01

Project Details

State

LA

County

St. Landry Parish

Region

MISO

Developer

Utility

CLECO POWER

Entity

MISO

Point of Interconnection

Ville Platte - West Fork 230.0kV

Data Source

LBNL + Live

No news available for this project.